23.05.2016  
  Realnoe Vremya,  
 

Innovation Project At Kazan CHP-3 Plant Continues


 
 

Construction of a new innovative energy generating unit based on a gas turbine unit (GTU) continues at Kazan CHP-3, a branch of TGK-16 OJSC.

As it has been revealed by Realnoe Vremya, currently the construction of the building for administrative and technical staff, where the main control desk of the unit and control systems electrical equipment will be located, is almost over.

Finishing and installation works are carried out intensively. In particular, fine and coarse filters, and a comprehensive air treatment system air heater are being installed at the comprehensive air filtering unit (AIU). Overhead crane is in the process of installation in the main building. Installation of auxiliary facilities and tank farms goes on. The gas turbine case installation is completed; this case is designed to limit the operating personnel's exposure to the turbine heat impact. The installation of temperature sensors and fans is in progress.

The construction of the main building and gas booster station is about to be completed at the moment. Besides, three gas compressors supplied by Atlas Copco, Germany, have been delivered to the construction site.

It will be recalled that the commissioning work is scheduled for the second half of 2016. This will provide a possibility to launch the unit in the 1st quarter of 2017 thereby doubling the installed electric power capacity of Kazan CHP-3.

the winner of the Best CBA contest in the category Enterprises and Organizations of the 1st Group Industries (2015), and the winner of the VI Best CBA republican contest in the category For Efficient Protection of The Youth's Social and Labor Rights (Industrial Enterprises and Organizations).

 
 
 

 

27, Shchapova Str.,
420012 Kazan, Republic of Tatarstan, Russia


Tel.: +7 (843) 277-94-02
Fax: +7 (843) 277-94-03
E-mail: bars@taif.ru